Introduction

Kortversjonen

Lytt til artikkelen

1. Introduction

The rules on subcontractor delay are usually about daybreak, and this is what will be our focus. It automatically follows from the standard contracts that the agreed end date is day-ahead unless otherwise agreed. It is also conceivable that the parties have agreed on other daylong deadlines and this is something we also discuss in the article on “Delay and Daybreak Liability”.

The rules on defects are also central to any construction project. From the point of view of experience, no construction or construction projects are erected without errors and shortcomings. Accordingly, it is necessary to devote some space to these rules with particular focus on the right and duty of the subcontractor to rectification. At the same time, we cannot write about shortcomings without also writing about the complaint rules. Therefore, we have given the article the title “Deficiencies and Complaints”.

Breaches of the obligation to coordinate are of greater relevance in subcontracting than in the overall standards such as projects that are most often organised today. There is far less degree of builder-led subcontracting now, than in the past. One consequence of this is that the obligation of (and the need for) coordination is far greater in the subcontracting relationship than it was perhaps in the past. We have therefore written a separate article on the consequences of breaches of the coordination obligation in subcontracting contracts.

2. Overview of the rules

All contract standards have their own provisions for delays and deficiencies. In NS 8417 these are collected in Chapter IX “Breach of contract on the part of TUE” and in NS 8415 one finds the provisions of Chapter VII “Delay. Missing”. In NS 8416, the rules are collected in two provisions. We start from NS 8417 since it is turnkey contracts that are most often used today — although NS 8415 can also be a reasonable alternative where the main contract is NS 8407, read more here.

Below we have taken a matrix showing the main provisions. Several of these have more detailed sub-provisions that we deal with in our own articles.

Introduction

Kortversjonen

Lytt til artikkelen

1. Introduction

The rules on subcontractor delay are usually about daybreak, and this is what will be our focus. It automatically follows from the standard contracts that the agreed end date is day-ahead unless otherwise agreed. It is also conceivable that the parties have agreed on other daylong deadlines and this is something we also discuss in the article on “Delay and Daybreak Liability”.

The rules on defects are also central to any construction project. From the point of view of experience, no construction or construction projects are erected without errors and shortcomings. Accordingly, it is necessary to devote some space to these rules with particular focus on the right and duty of the subcontractor to rectification. At the same time, we cannot write about shortcomings without also writing about the complaint rules. Therefore, we have given the article the title “Deficiencies and Complaints”.

Breaches of the obligation to coordinate are of greater relevance in subcontracting than in the overall standards such as projects that are most often organised today. There is far less degree of builder-led subcontracting now, than in the past. One consequence of this is that the obligation of (and the need for) coordination is far greater in the subcontracting relationship than it was perhaps in the past. We have therefore written a separate article on the consequences of breaches of the coordination obligation in subcontracting contracts.

2. Overview of the rules

All contract standards have their own provisions for delays and deficiencies. In NS 8417 these are collected in Chapter IX “Breach of contract on the part of TUE” and in NS 8415 one finds the provisions of Chapter VII “Delay. Missing”. In NS 8416, the rules are collected in two provisions. We start from NS 8417 since it is turnkey contracts that are most often used today — although NS 8415 can also be a reasonable alternative where the main contract is NS 8407, read more here.

Below we have taken a matrix showing the main provisions. Several of these have more detailed sub-provisions that we deal with in our own articles.

Introduction

Kortversjonen

Lytt til artikkelen

1. Introduction

The rules on subcontractor delay are usually about daybreak, and this is what will be our focus. It automatically follows from the standard contracts that the agreed end date is day-ahead unless otherwise agreed. It is also conceivable that the parties have agreed on other daylong deadlines and this is something we also discuss in the article on “Delay and Daybreak Liability”.

The rules on defects are also central to any construction project. From the point of view of experience, no construction or construction projects are erected without errors and shortcomings. Accordingly, it is necessary to devote some space to these rules with particular focus on the right and duty of the subcontractor to rectification. At the same time, we cannot write about shortcomings without also writing about the complaint rules. Therefore, we have given the article the title “Deficiencies and Complaints”.

Breaches of the obligation to coordinate are of greater relevance in subcontracting than in the overall standards such as projects that are most often organised today. There is far less degree of builder-led subcontracting now, than in the past. One consequence of this is that the obligation of (and the need for) coordination is far greater in the subcontracting relationship than it was perhaps in the past. We have therefore written a separate article on the consequences of breaches of the coordination obligation in subcontracting contracts.

2. Overview of the rules

All contract standards have their own provisions for delays and deficiencies. In NS 8417 these are collected in Chapter IX “Breach of contract on the part of TUE” and in NS 8415 one finds the provisions of Chapter VII “Delay. Missing”. In NS 8416, the rules are collected in two provisions. We start from NS 8417 since it is turnkey contracts that are most often used today — although NS 8415 can also be a reasonable alternative where the main contract is NS 8407, read more here.

Below we have taken a matrix showing the main provisions. Several of these have more detailed sub-provisions that we deal with in our own articles.

Introduction

Kortversjonen

Lytt til artikkelen

1. Introduction

The rules on subcontractor delay are usually about daybreak, and this is what will be our focus. It automatically follows from the standard contracts that the agreed end date is day-ahead unless otherwise agreed. It is also conceivable that the parties have agreed on other daylong deadlines and this is something we also discuss in the article on “Delay and Daybreak Liability”.

The rules on defects are also central to any construction project. From the point of view of experience, no construction or construction projects are erected without errors and shortcomings. Accordingly, it is necessary to devote some space to these rules with particular focus on the right and duty of the subcontractor to rectification. At the same time, we cannot write about shortcomings without also writing about the complaint rules. Therefore, we have given the article the title “Deficiencies and Complaints”.

Breaches of the obligation to coordinate are of greater relevance in subcontracting than in the overall standards such as projects that are most often organised today. There is far less degree of builder-led subcontracting now, than in the past. One consequence of this is that the obligation of (and the need for) coordination is far greater in the subcontracting relationship than it was perhaps in the past. We have therefore written a separate article on the consequences of breaches of the coordination obligation in subcontracting contracts.

2. Overview of the rules

All contract standards have their own provisions for delays and deficiencies. In NS 8417 these are collected in Chapter IX “Breach of contract on the part of TUE” and in NS 8415 one finds the provisions of Chapter VII “Delay. Missing”. In NS 8416, the rules are collected in two provisions. We start from NS 8417 since it is turnkey contracts that are most often used today — although NS 8415 can also be a reasonable alternative where the main contract is NS 8407, read more here.

Below we have taken a matrix showing the main provisions. Several of these have more detailed sub-provisions that we deal with in our own articles.

Introduction

Kortversjonen

Lytt til artikkelen

1. Introduction

The rules on subcontractor delay are usually about daybreak, and this is what will be our focus. It automatically follows from the standard contracts that the agreed end date is day-ahead unless otherwise agreed. It is also conceivable that the parties have agreed on other daylong deadlines and this is something we also discuss in the article on “Delay and Daybreak Liability”.

The rules on defects are also central to any construction project. From the point of view of experience, no construction or construction projects are erected without errors and shortcomings. Accordingly, it is necessary to devote some space to these rules with particular focus on the right and duty of the subcontractor to rectification. At the same time, we cannot write about shortcomings without also writing about the complaint rules. Therefore, we have given the article the title “Deficiencies and Complaints”.

Breaches of the obligation to coordinate are of greater relevance in subcontracting than in the overall standards such as projects that are most often organised today. There is far less degree of builder-led subcontracting now, than in the past. One consequence of this is that the obligation of (and the need for) coordination is far greater in the subcontracting relationship than it was perhaps in the past. We have therefore written a separate article on the consequences of breaches of the coordination obligation in subcontracting contracts.

2. Overview of the rules

All contract standards have their own provisions for delays and deficiencies. In NS 8417 these are collected in Chapter IX “Breach of contract on the part of TUE” and in NS 8415 one finds the provisions of Chapter VII “Delay. Missing”. In NS 8416, the rules are collected in two provisions. We start from NS 8417 since it is turnkey contracts that are most often used today — although NS 8415 can also be a reasonable alternative where the main contract is NS 8407, read more here.

Below we have taken a matrix showing the main provisions. Several of these have more detailed sub-provisions that we deal with in our own articles.

Introduction

Kortversjonen

1. Introduction

The rules on subcontractor delay are usually about daybreak, and this is what will be our focus. It automatically follows from the standard contracts that the agreed end date is day-ahead unless otherwise agreed. It is also conceivable that the parties have agreed on other daylong deadlines and this is something we also discuss in the article on “Delay and Daybreak Liability”.

The rules on defects are also central to any construction project. From the point of view of experience, no construction or construction projects are erected without errors and shortcomings. Accordingly, it is necessary to devote some space to these rules with particular focus on the right and duty of the subcontractor to rectification. At the same time, we cannot write about shortcomings without also writing about the complaint rules. Therefore, we have given the article the title “Deficiencies and Complaints”.

Breaches of the obligation to coordinate are of greater relevance in subcontracting than in the overall standards such as projects that are most often organised today. There is far less degree of builder-led subcontracting now, than in the past. One consequence of this is that the obligation of (and the need for) coordination is far greater in the subcontracting relationship than it was perhaps in the past. We have therefore written a separate article on the consequences of breaches of the coordination obligation in subcontracting contracts.

2. Overview of the rules

All contract standards have their own provisions for delays and deficiencies. In NS 8417 these are collected in Chapter IX “Breach of contract on the part of TUE” and in NS 8415 one finds the provisions of Chapter VII “Delay. Missing”. In NS 8416, the rules are collected in two provisions. We start from NS 8417 since it is turnkey contracts that are most often used today — although NS 8415 can also be a reasonable alternative where the main contract is NS 8407, read more here.

Below we have taken a matrix showing the main provisions. Several of these have more detailed sub-provisions that we deal with in our own articles.

Spar 20% ved årlig betaling

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Nåværene plan
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Bytt til månedlig abonnement
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Bytt til årsabonnement
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedsabonnement

kr 990,– / mnd
Trekkes hver måned
Nåværende plan
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til nye e-kurs som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår
Spar 20% ved årlig betaling

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Nåværene plan
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Bytt til månedlig abonnement
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Bytt til årsabonnement
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedsabonnement

kr 990,– / mnd
Trekkes hver måned
Nåværende plan
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til nye e-kurs som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår

Har du et tema du ønsker at vi skal skrive om?

Thank you! Your submission has been received!
Det skjedde noe galt. Kontakt oss på hei@byggogprosjektjus.no hvis problemet vedvarer

Har du et tema du ønsker at vi skal skrive om?

Thank you! Your submission has been received!
Det skjedde noe galt. Kontakt oss på hei@byggogprosjektjus.no hvis problemet vedvarer