Introduction

Kortversjonen

Lytt til artikkelen

1. Introduction

The provisions on the benefits of the builder include various conditions.

Some of the provisions deal with actual services such as materials supplied or determined by the builder, or design carried out by the developer, whether up to the conclusion of a contract with the general contractor and/ or in parallel with the execution of the main contractor.

In other cases, there is more talk of the builder's benefits in an indirect sense in that in reality there is more talk of having the risk of conditions neither the builder nor the contractor is aware of.

This is the situation when it comes to the physical work base that the builder makes available to the contractor, and where the builder has, by default, disclosed everything he knows about.

Similarly, it deals with unforeseen circumstances in the ground. Nor are there matters that it is really natural to characterize as builder performance in the literal sense, but rather about risk placement for the unknown.

2. Overview of the rules

As for all other topics, we start from NS 8407 because it is this contract standard that is used most often today.

Below we have included a matrix in which we show the individual provisions as stated in the three standard contracts.

We have (for now) written two articles on this topic, namely about 1)the risk of conditions at the ground and the physical base of work; and ! 2)the builder's engineering and agreed risk transition.

Our impression is that the other provisions do not create major challenges in practice, but aim to complement as we develop the content even more.

Introduction

Kortversjonen

Lytt til artikkelen

1. Introduction

The provisions on the benefits of the builder include various conditions.

Some of the provisions deal with actual services such as materials supplied or determined by the builder, or design carried out by the developer, whether up to the conclusion of a contract with the general contractor and/ or in parallel with the execution of the main contractor.

In other cases, there is more talk of the builder's benefits in an indirect sense in that in reality there is more talk of having the risk of conditions neither the builder nor the contractor is aware of.

This is the situation when it comes to the physical work base that the builder makes available to the contractor, and where the builder has, by default, disclosed everything he knows about.

Similarly, it deals with unforeseen circumstances in the ground. Nor are there matters that it is really natural to characterize as builder performance in the literal sense, but rather about risk placement for the unknown.

2. Overview of the rules

As for all other topics, we start from NS 8407 because it is this contract standard that is used most often today.

Below we have included a matrix in which we show the individual provisions as stated in the three standard contracts.

We have (for now) written two articles on this topic, namely about 1)the risk of conditions at the ground and the physical base of work; and ! 2)the builder's engineering and agreed risk transition.

Our impression is that the other provisions do not create major challenges in practice, but aim to complement as we develop the content even more.

Introduction

Kortversjonen

Lytt til artikkelen

1. Introduction

The provisions on the benefits of the builder include various conditions.

Some of the provisions deal with actual services such as materials supplied or determined by the builder, or design carried out by the developer, whether up to the conclusion of a contract with the general contractor and/ or in parallel with the execution of the main contractor.

In other cases, there is more talk of the builder's benefits in an indirect sense in that in reality there is more talk of having the risk of conditions neither the builder nor the contractor is aware of.

This is the situation when it comes to the physical work base that the builder makes available to the contractor, and where the builder has, by default, disclosed everything he knows about.

Similarly, it deals with unforeseen circumstances in the ground. Nor are there matters that it is really natural to characterize as builder performance in the literal sense, but rather about risk placement for the unknown.

2. Overview of the rules

As for all other topics, we start from NS 8407 because it is this contract standard that is used most often today.

Below we have included a matrix in which we show the individual provisions as stated in the three standard contracts.

We have (for now) written two articles on this topic, namely about 1)the risk of conditions at the ground and the physical base of work; and ! 2)the builder's engineering and agreed risk transition.

Our impression is that the other provisions do not create major challenges in practice, but aim to complement as we develop the content even more.

Introduction

Kortversjonen

Lytt til artikkelen

1. Introduction

The provisions on the benefits of the builder include various conditions.

Some of the provisions deal with actual services such as materials supplied or determined by the builder, or design carried out by the developer, whether up to the conclusion of a contract with the general contractor and/ or in parallel with the execution of the main contractor.

In other cases, there is more talk of the builder's benefits in an indirect sense in that in reality there is more talk of having the risk of conditions neither the builder nor the contractor is aware of.

This is the situation when it comes to the physical work base that the builder makes available to the contractor, and where the builder has, by default, disclosed everything he knows about.

Similarly, it deals with unforeseen circumstances in the ground. Nor are there matters that it is really natural to characterize as builder performance in the literal sense, but rather about risk placement for the unknown.

2. Overview of the rules

As for all other topics, we start from NS 8407 because it is this contract standard that is used most often today.

Below we have included a matrix in which we show the individual provisions as stated in the three standard contracts.

We have (for now) written two articles on this topic, namely about 1)the risk of conditions at the ground and the physical base of work; and ! 2)the builder's engineering and agreed risk transition.

Our impression is that the other provisions do not create major challenges in practice, but aim to complement as we develop the content even more.

Introduction

Kortversjonen

Lytt til artikkelen

1. Introduction

The provisions on the benefits of the builder include various conditions.

Some of the provisions deal with actual services such as materials supplied or determined by the builder, or design carried out by the developer, whether up to the conclusion of a contract with the general contractor and/ or in parallel with the execution of the main contractor.

In other cases, there is more talk of the builder's benefits in an indirect sense in that in reality there is more talk of having the risk of conditions neither the builder nor the contractor is aware of.

This is the situation when it comes to the physical work base that the builder makes available to the contractor, and where the builder has, by default, disclosed everything he knows about.

Similarly, it deals with unforeseen circumstances in the ground. Nor are there matters that it is really natural to characterize as builder performance in the literal sense, but rather about risk placement for the unknown.

2. Overview of the rules

As for all other topics, we start from NS 8407 because it is this contract standard that is used most often today.

Below we have included a matrix in which we show the individual provisions as stated in the three standard contracts.

We have (for now) written two articles on this topic, namely about 1)the risk of conditions at the ground and the physical base of work; and ! 2)the builder's engineering and agreed risk transition.

Our impression is that the other provisions do not create major challenges in practice, but aim to complement as we develop the content even more.

Introduction

Kortversjonen

1. Introduction

The provisions on the benefits of the builder include various conditions.

Some of the provisions deal with actual services such as materials supplied or determined by the builder, or design carried out by the developer, whether up to the conclusion of a contract with the general contractor and/ or in parallel with the execution of the main contractor.

In other cases, there is more talk of the builder's benefits in an indirect sense in that in reality there is more talk of having the risk of conditions neither the builder nor the contractor is aware of.

This is the situation when it comes to the physical work base that the builder makes available to the contractor, and where the builder has, by default, disclosed everything he knows about.

Similarly, it deals with unforeseen circumstances in the ground. Nor are there matters that it is really natural to characterize as builder performance in the literal sense, but rather about risk placement for the unknown.

2. Overview of the rules

As for all other topics, we start from NS 8407 because it is this contract standard that is used most often today.

Below we have included a matrix in which we show the individual provisions as stated in the three standard contracts.

We have (for now) written two articles on this topic, namely about 1)the risk of conditions at the ground and the physical base of work; and ! 2)the builder's engineering and agreed risk transition.

Our impression is that the other provisions do not create major challenges in practice, but aim to complement as we develop the content even more.

Abonner og få tilgang til hele artikkelen og mye mer!

Spar opp til 40% ved årlig betaling

Kunnskapsbank

kr 990,– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

E-kurs

kr 490,– / mnd
Trekkes årlig
Kun tilgjengelig som årlig abonnement
  • Tilgang til alle e-kurs
  • Tilgang til nye e-læringsmoduler som publiseres

Kunnskapsbank + E-kurs

kr 790,– / mnd
Trekkes årlig
Kun tilgjengelig som årlig abonnement
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Spar opp til 40% ved årlig betaling

Kunnskapsbank

kr 590,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

E-kurs

kr 490,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle e-kurs
  • Tilgang til nye e-læringsmoduler som publiseres

Kunnskapsbank + E-kurs

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår

Abonner og få tilgang til hele artikkelen og mye mer!

Spar opp til 40% ved årlig betaling

Kunnskapsbank

kr 990,– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

E-kurs

kr 490,– / mnd
Trekkes årlig
Kun tilgjengelig som årlig abonnement
  • Tilgang til alle e-kurs
  • Tilgang til nye e-læringsmoduler som publiseres

Kunnskapsbank + E-kurs

kr 790,– / mnd
Trekkes årlig
Kun tilgjengelig som årlig abonnement
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Spar opp til 40% ved årlig betaling

Kunnskapsbank

kr 590,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

E-kurs

kr 490,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle e-kurs
  • Tilgang til nye e-læringsmoduler som publiseres

Kunnskapsbank + E-kurs

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår

Abonner og få tilgang til hele artikkelen og mye mer!

Spar opp til 40% ved årlig betaling

E-kurs

kr 490,–
Trekkes årlig
Nåværende plan
  • Tilgang til alle e-kurs
  • Tilgang til nye e-kurs som publiseres

Kunnskapsbank

kr 990,– / mnd
Trekkes hver måned
Legg til
  • Tilgang til 79 artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Spar opp til 40% ved årlig betaling

E-kurs

kr 490,– / mnd
Trekkes årlig
Nåværende plan
  • Tilgang til alle e-kurs
  • Tilgang til nye e-kurs som publiseres

Kunnskapsbank

kr 300,– / mnd
Trekkes årlig
Legg til
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår

Har du et tema du ønsker at vi skal skrive om?

Thank you! Your submission has been received!
Det skjedde noe galt. Kontakt oss på hei@byggogprosjektjus.no hvis problemet vedvarer

Har du et tema du ønsker at vi skal skrive om?

Thank you! Your submission has been received!
Det skjedde noe galt. Kontakt oss på hei@byggogprosjektjus.no hvis problemet vedvarer