Introduction

Kortversjonen

Lytt til artikkelen

The provisions on the benefits of the main/general contractor are found in NS 8415 chapter III, NS 8416 paragraph 18 and NS 8417 chapter V.

There is quite a difference between NS 8417 and the two standards in terms of what is dealt with under this topic, and therefore it is not natural to compare. We have therefore not put the provisions into a matrix.

In NS 8417, there are four main categories, namely “Participation of the general contractor” (22), “The Risks of Relationships at the Ground” (23), “The general contractor's choice of solutions and other engineering” (24) and “TUE's review of general contractor benefits. Obligation to notify” (25).

In NS 8415, there are three main categories, namely “Content of the General Contractor's Participation Obligation” (19), “Time of participation of the general contractor” (20) and “Subcontractor's duty to notify” (21).

In NS 8416 it is only one category, namely “Performance of the General Contractor” (18).

We have written two articles dealing with the provisions and topics that in practice create the greatest challenges.

It concerns 1) The risk of conditions at the ground and the physical base of work and ! 2) “Main/General Contractor's engineering and agreed risk transition”.

Introduction

Kortversjonen

Lytt til artikkelen

The provisions on the benefits of the main/general contractor are found in NS 8415 chapter III, NS 8416 paragraph 18 and NS 8417 chapter V.

There is quite a difference between NS 8417 and the two standards in terms of what is dealt with under this topic, and therefore it is not natural to compare. We have therefore not put the provisions into a matrix.

In NS 8417, there are four main categories, namely “Participation of the general contractor” (22), “The Risks of Relationships at the Ground” (23), “The general contractor's choice of solutions and other engineering” (24) and “TUE's review of general contractor benefits. Obligation to notify” (25).

In NS 8415, there are three main categories, namely “Content of the General Contractor's Participation Obligation” (19), “Time of participation of the general contractor” (20) and “Subcontractor's duty to notify” (21).

In NS 8416 it is only one category, namely “Performance of the General Contractor” (18).

We have written two articles dealing with the provisions and topics that in practice create the greatest challenges.

It concerns 1) The risk of conditions at the ground and the physical base of work and ! 2) “Main/General Contractor's engineering and agreed risk transition”.

Introduction

Kortversjonen

Lytt til artikkelen

The provisions on the benefits of the main/general contractor are found in NS 8415 chapter III, NS 8416 paragraph 18 and NS 8417 chapter V.

There is quite a difference between NS 8417 and the two standards in terms of what is dealt with under this topic, and therefore it is not natural to compare. We have therefore not put the provisions into a matrix.

In NS 8417, there are four main categories, namely “Participation of the general contractor” (22), “The Risks of Relationships at the Ground” (23), “The general contractor's choice of solutions and other engineering” (24) and “TUE's review of general contractor benefits. Obligation to notify” (25).

In NS 8415, there are three main categories, namely “Content of the General Contractor's Participation Obligation” (19), “Time of participation of the general contractor” (20) and “Subcontractor's duty to notify” (21).

In NS 8416 it is only one category, namely “Performance of the General Contractor” (18).

We have written two articles dealing with the provisions and topics that in practice create the greatest challenges.

It concerns 1) The risk of conditions at the ground and the physical base of work and ! 2) “Main/General Contractor's engineering and agreed risk transition”.

Introduction

Kortversjonen

Lytt til artikkelen

The provisions on the benefits of the main/general contractor are found in NS 8415 chapter III, NS 8416 paragraph 18 and NS 8417 chapter V.

There is quite a difference between NS 8417 and the two standards in terms of what is dealt with under this topic, and therefore it is not natural to compare. We have therefore not put the provisions into a matrix.

In NS 8417, there are four main categories, namely “Participation of the general contractor” (22), “The Risks of Relationships at the Ground” (23), “The general contractor's choice of solutions and other engineering” (24) and “TUE's review of general contractor benefits. Obligation to notify” (25).

In NS 8415, there are three main categories, namely “Content of the General Contractor's Participation Obligation” (19), “Time of participation of the general contractor” (20) and “Subcontractor's duty to notify” (21).

In NS 8416 it is only one category, namely “Performance of the General Contractor” (18).

We have written two articles dealing with the provisions and topics that in practice create the greatest challenges.

It concerns 1) The risk of conditions at the ground and the physical base of work and ! 2) “Main/General Contractor's engineering and agreed risk transition”.

Introduction

Kortversjonen

Lytt til artikkelen

The provisions on the benefits of the main/general contractor are found in NS 8415 chapter III, NS 8416 paragraph 18 and NS 8417 chapter V.

There is quite a difference between NS 8417 and the two standards in terms of what is dealt with under this topic, and therefore it is not natural to compare. We have therefore not put the provisions into a matrix.

In NS 8417, there are four main categories, namely “Participation of the general contractor” (22), “The Risks of Relationships at the Ground” (23), “The general contractor's choice of solutions and other engineering” (24) and “TUE's review of general contractor benefits. Obligation to notify” (25).

In NS 8415, there are three main categories, namely “Content of the General Contractor's Participation Obligation” (19), “Time of participation of the general contractor” (20) and “Subcontractor's duty to notify” (21).

In NS 8416 it is only one category, namely “Performance of the General Contractor” (18).

We have written two articles dealing with the provisions and topics that in practice create the greatest challenges.

It concerns 1) The risk of conditions at the ground and the physical base of work and ! 2) “Main/General Contractor's engineering and agreed risk transition”.

Introduction

Kortversjonen

The provisions on the benefits of the main/general contractor are found in NS 8415 chapter III, NS 8416 paragraph 18 and NS 8417 chapter V.

There is quite a difference between NS 8417 and the two standards in terms of what is dealt with under this topic, and therefore it is not natural to compare. We have therefore not put the provisions into a matrix.

In NS 8417, there are four main categories, namely “Participation of the general contractor” (22), “The Risks of Relationships at the Ground” (23), “The general contractor's choice of solutions and other engineering” (24) and “TUE's review of general contractor benefits. Obligation to notify” (25).

In NS 8415, there are three main categories, namely “Content of the General Contractor's Participation Obligation” (19), “Time of participation of the general contractor” (20) and “Subcontractor's duty to notify” (21).

In NS 8416 it is only one category, namely “Performance of the General Contractor” (18).

We have written two articles dealing with the provisions and topics that in practice create the greatest challenges.

It concerns 1) The risk of conditions at the ground and the physical base of work and ! 2) “Main/General Contractor's engineering and agreed risk transition”.

Spar 20% ved årlig betaling

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Nåværene plan
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Bytt til månedlig abonnement
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Bytt til årsabonnement
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedsabonnement

kr 990,– / mnd
Trekkes hver måned
Nåværende plan
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til nye e-kurs som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår
Spar 20% ved årlig betaling

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Nåværene plan
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedlig abonnement

kr 990,– / mnd
Trekkes hver måned
Bytt til månedlig abonnement
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Tilgang til alle e-kurs
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Årsabonnement

kr 790,– / mnd
Trekkes årlig
Bytt til årsabonnement
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år

Månedsabonnement

kr 990,– / mnd
Trekkes hver måned
Nåværende plan
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til nye e-kurs som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår

Har du et tema du ønsker at vi skal skrive om?

Thank you! Your submission has been received!
Det skjedde noe galt. Kontakt oss på hei@byggogprosjektjus.no hvis problemet vedvarer

Har du et tema du ønsker at vi skal skrive om?

Thank you! Your submission has been received!
Det skjedde noe galt. Kontakt oss på hei@byggogprosjektjus.no hvis problemet vedvarer