Introduction

Kortversjonen

1. Introduction

As one approaches the time of handover one moves into the closing phase.

Experientially, there can be experienced to be many “arms and legs” in this phase. Most subjects are busy finishing their works while there are often a number of dependencies between the respective subjects. This phase therefore places great demands on good progress planning and coordination — usually from day to day.

At the same time as a number of final and complementary works are underway, we are entering the period when technical systems will be tested. Often, such tests assume that most of the work is completed. When testing ventilation systems, you do not want dust and particles to be sucked into ducts and clog filters, which requires a clean dry building. Fire alarm systems assume that doors are left open or closed and this again assumes that all electronic door locks etc. are complete. The more extensive and complex the more time one will need.

This phase is therefore of great importance to all parties. One is approaching the “moment of truth,” namely the takeover business.

As is known, when the build/ facility is taken over, the risk passes to the builder and the contractor gets the right to submit a claim for final settlement. In addition, the entrepreneur avoids daybreak if the takeover business starts within the agreed closing deadline.

It is no coincidence that the most detailed and comprehensive provisions are contained in NS 8417, and this is related to the fact that the total subcontractor has the functional risk.

2. Overview of the rules

Below we have adopted a matrix showing the individual topics and as before we start from NS 8417 since it is this contract standard that is most often used today. We still get into NS 8415 and NS 8416 where this is natural.

In the subcontracting standards there are rules on registration business.

This is a business that a subcontractor can demand to be completed when he has finished his works, and at the same time it will take some time before the main/general contractor will hand over the overall works to the builder. It is the case that the subcontractor's works are not formally handed over to the main/general contractor until the latter hands over to the builder. This, in turn, is a consequence of a “back to back” thinking in which the guarantee period of all contractors should start running at the same time, namely when the builder takes over from the main/general contractor.

We have written four articles that deal with the different phases, namely about 1) registration business, whether (2)preparation for takeover, if (3) the takeover business itself and whether 4th) the final settlement.

Introduction

Kortversjonen

1. Introduction

As one approaches the time of handover one moves into the closing phase.

Experientially, there can be experienced to be many “arms and legs” in this phase. Most subjects are busy finishing their works while there are often a number of dependencies between the respective subjects. This phase therefore places great demands on good progress planning and coordination — usually from day to day.

At the same time as a number of final and complementary works are underway, we are entering the period when technical systems will be tested. Often, such tests assume that most of the work is completed. When testing ventilation systems, you do not want dust and particles to be sucked into ducts and clog filters, which requires a clean dry building. Fire alarm systems assume that doors are left open or closed and this again assumes that all electronic door locks etc. are complete. The more extensive and complex the more time one will need.

This phase is therefore of great importance to all parties. One is approaching the “moment of truth,” namely the takeover business.

As is known, when the build/ facility is taken over, the risk passes to the builder and the contractor gets the right to submit a claim for final settlement. In addition, the entrepreneur avoids daybreak if the takeover business starts within the agreed closing deadline.

It is no coincidence that the most detailed and comprehensive provisions are contained in NS 8417, and this is related to the fact that the total subcontractor has the functional risk.

2. Overview of the rules

Below we have adopted a matrix showing the individual topics and as before we start from NS 8417 since it is this contract standard that is most often used today. We still get into NS 8415 and NS 8416 where this is natural.

In the subcontracting standards there are rules on registration business.

This is a business that a subcontractor can demand to be completed when he has finished his works, and at the same time it will take some time before the main/general contractor will hand over the overall works to the builder. It is the case that the subcontractor's works are not formally handed over to the main/general contractor until the latter hands over to the builder. This, in turn, is a consequence of a “back to back” thinking in which the guarantee period of all contractors should start running at the same time, namely when the builder takes over from the main/general contractor.

We have written four articles that deal with the different phases, namely about 1) registration business, whether (2)preparation for takeover, if (3) the takeover business itself and whether 4th) the final settlement.

Introduction

Kortversjonen

1. Introduction

As one approaches the time of handover one moves into the closing phase.

Experientially, there can be experienced to be many “arms and legs” in this phase. Most subjects are busy finishing their works while there are often a number of dependencies between the respective subjects. This phase therefore places great demands on good progress planning and coordination — usually from day to day.

At the same time as a number of final and complementary works are underway, we are entering the period when technical systems will be tested. Often, such tests assume that most of the work is completed. When testing ventilation systems, you do not want dust and particles to be sucked into ducts and clog filters, which requires a clean dry building. Fire alarm systems assume that doors are left open or closed and this again assumes that all electronic door locks etc. are complete. The more extensive and complex the more time one will need.

This phase is therefore of great importance to all parties. One is approaching the “moment of truth,” namely the takeover business.

As is known, when the build/ facility is taken over, the risk passes to the builder and the contractor gets the right to submit a claim for final settlement. In addition, the entrepreneur avoids daybreak if the takeover business starts within the agreed closing deadline.

It is no coincidence that the most detailed and comprehensive provisions are contained in NS 8417, and this is related to the fact that the total subcontractor has the functional risk.

2. Overview of the rules

Below we have adopted a matrix showing the individual topics and as before we start from NS 8417 since it is this contract standard that is most often used today. We still get into NS 8415 and NS 8416 where this is natural.

In the subcontracting standards there are rules on registration business.

This is a business that a subcontractor can demand to be completed when he has finished his works, and at the same time it will take some time before the main/general contractor will hand over the overall works to the builder. It is the case that the subcontractor's works are not formally handed over to the main/general contractor until the latter hands over to the builder. This, in turn, is a consequence of a “back to back” thinking in which the guarantee period of all contractors should start running at the same time, namely when the builder takes over from the main/general contractor.

We have written four articles that deal with the different phases, namely about 1) registration business, whether (2)preparation for takeover, if (3) the takeover business itself and whether 4th) the final settlement.

Introduction

Kortversjonen

1. Introduction

As one approaches the time of handover one moves into the closing phase.

Experientially, there can be experienced to be many “arms and legs” in this phase. Most subjects are busy finishing their works while there are often a number of dependencies between the respective subjects. This phase therefore places great demands on good progress planning and coordination — usually from day to day.

At the same time as a number of final and complementary works are underway, we are entering the period when technical systems will be tested. Often, such tests assume that most of the work is completed. When testing ventilation systems, you do not want dust and particles to be sucked into ducts and clog filters, which requires a clean dry building. Fire alarm systems assume that doors are left open or closed and this again assumes that all electronic door locks etc. are complete. The more extensive and complex the more time one will need.

This phase is therefore of great importance to all parties. One is approaching the “moment of truth,” namely the takeover business.

As is known, when the build/ facility is taken over, the risk passes to the builder and the contractor gets the right to submit a claim for final settlement. In addition, the entrepreneur avoids daybreak if the takeover business starts within the agreed closing deadline.

It is no coincidence that the most detailed and comprehensive provisions are contained in NS 8417, and this is related to the fact that the total subcontractor has the functional risk.

2. Overview of the rules

Below we have adopted a matrix showing the individual topics and as before we start from NS 8417 since it is this contract standard that is most often used today. We still get into NS 8415 and NS 8416 where this is natural.

In the subcontracting standards there are rules on registration business.

This is a business that a subcontractor can demand to be completed when he has finished his works, and at the same time it will take some time before the main/general contractor will hand over the overall works to the builder. It is the case that the subcontractor's works are not formally handed over to the main/general contractor until the latter hands over to the builder. This, in turn, is a consequence of a “back to back” thinking in which the guarantee period of all contractors should start running at the same time, namely when the builder takes over from the main/general contractor.

We have written four articles that deal with the different phases, namely about 1) registration business, whether (2)preparation for takeover, if (3) the takeover business itself and whether 4th) the final settlement.

Introduction

Kortversjonen

1. Introduction

As one approaches the time of handover one moves into the closing phase.

Experientially, there can be experienced to be many “arms and legs” in this phase. Most subjects are busy finishing their works while there are often a number of dependencies between the respective subjects. This phase therefore places great demands on good progress planning and coordination — usually from day to day.

At the same time as a number of final and complementary works are underway, we are entering the period when technical systems will be tested. Often, such tests assume that most of the work is completed. When testing ventilation systems, you do not want dust and particles to be sucked into ducts and clog filters, which requires a clean dry building. Fire alarm systems assume that doors are left open or closed and this again assumes that all electronic door locks etc. are complete. The more extensive and complex the more time one will need.

This phase is therefore of great importance to all parties. One is approaching the “moment of truth,” namely the takeover business.

As is known, when the build/ facility is taken over, the risk passes to the builder and the contractor gets the right to submit a claim for final settlement. In addition, the entrepreneur avoids daybreak if the takeover business starts within the agreed closing deadline.

It is no coincidence that the most detailed and comprehensive provisions are contained in NS 8417, and this is related to the fact that the total subcontractor has the functional risk.

2. Overview of the rules

Below we have adopted a matrix showing the individual topics and as before we start from NS 8417 since it is this contract standard that is most often used today. We still get into NS 8415 and NS 8416 where this is natural.

In the subcontracting standards there are rules on registration business.

This is a business that a subcontractor can demand to be completed when he has finished his works, and at the same time it will take some time before the main/general contractor will hand over the overall works to the builder. It is the case that the subcontractor's works are not formally handed over to the main/general contractor until the latter hands over to the builder. This, in turn, is a consequence of a “back to back” thinking in which the guarantee period of all contractors should start running at the same time, namely when the builder takes over from the main/general contractor.

We have written four articles that deal with the different phases, namely about 1) registration business, whether (2)preparation for takeover, if (3) the takeover business itself and whether 4th) the final settlement.

Introduction

Kortversjonen

1. Introduction

As one approaches the time of handover one moves into the closing phase.

Experientially, there can be experienced to be many “arms and legs” in this phase. Most subjects are busy finishing their works while there are often a number of dependencies between the respective subjects. This phase therefore places great demands on good progress planning and coordination — usually from day to day.

At the same time as a number of final and complementary works are underway, we are entering the period when technical systems will be tested. Often, such tests assume that most of the work is completed. When testing ventilation systems, you do not want dust and particles to be sucked into ducts and clog filters, which requires a clean dry building. Fire alarm systems assume that doors are left open or closed and this again assumes that all electronic door locks etc. are complete. The more extensive and complex the more time one will need.

This phase is therefore of great importance to all parties. One is approaching the “moment of truth,” namely the takeover business.

As is known, when the build/ facility is taken over, the risk passes to the builder and the contractor gets the right to submit a claim for final settlement. In addition, the entrepreneur avoids daybreak if the takeover business starts within the agreed closing deadline.

It is no coincidence that the most detailed and comprehensive provisions are contained in NS 8417, and this is related to the fact that the total subcontractor has the functional risk.

2. Overview of the rules

Below we have adopted a matrix showing the individual topics and as before we start from NS 8417 since it is this contract standard that is most often used today. We still get into NS 8415 and NS 8416 where this is natural.

In the subcontracting standards there are rules on registration business.

This is a business that a subcontractor can demand to be completed when he has finished his works, and at the same time it will take some time before the main/general contractor will hand over the overall works to the builder. It is the case that the subcontractor's works are not formally handed over to the main/general contractor until the latter hands over to the builder. This, in turn, is a consequence of a “back to back” thinking in which the guarantee period of all contractors should start running at the same time, namely when the builder takes over from the main/general contractor.

We have written four articles that deal with the different phases, namely about 1) registration business, whether (2)preparation for takeover, if (3) the takeover business itself and whether 4th) the final settlement.

Abonner og få tilgang til hele artikkelen og mye mer!

Spar opp til 40% ved årlig betaling

Kunnskapsbank

kr 490,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

E-kurs

kr 490,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle e-kurs
  • Tilgang til nye e-læringsmoduler som publiseres

Kunnskapsbank + E-kurs

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Spar opp til 40% ved årlig betaling

Kunnskapsbank

kr 490,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

E-kurs

kr 490,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle e-kurs
  • Tilgang til nye e-læringsmoduler som publiseres

Kunnskapsbank + E-kurs

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår

Abonner og få tilgang til hele artikkelen og mye mer!

Spar opp til 40% ved årlig betaling

Kunnskapsbank

kr 875– / mnd
Trekkes hver måned
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

E-kurs

kr 490,– / mnd
Trekkes årlig
Kun tilgjengelig som årlig abonnement
  • Tilgang til alle e-kurs
  • Tilgang til nye e-læringsmoduler som publiseres

Kunnskapsbank + E-kurs

kr 790,– / mnd
Trekkes årlig
Kun tilgjengelig som årlig abonnement
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Spar opp til 40% ved årlig betaling

Kunnskapsbank

kr 490,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år

E-kurs

kr 490,– / mnd
Trekkes årlig
Kom i gang
  • Tilgang til alle e-kurs
  • Tilgang til nye e-læringsmoduler som publiseres

Kunnskapsbank + E-kurs

kr 790,– / mnd
Trekkes årlig
Kom i gang
Beste tilbud
  • Tilgang til alle artikler
  • Tilgang til alle e-kurs
  • Tilgang til alt nytt innhold som publiseres.
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår

Abonner og få tilgang til hele artikkelen og mye mer!

Spar opp til 40% ved årlig betaling

E-kurs

kr 490,–
Trekkes årlig
Nåværende plan
  • Tilgang til alle e-kurs
  • Tilgang til nye e-kurs som publiseres

Kunnskapsbank

kr 875,– / mnd
Trekkes hver måned
Legg til
  • Tilgang til 79 artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Spar opp til 40% ved årlig betaling

E-kurs

kr 490,– / mnd
Trekkes årlig
Nåværende plan
  • Tilgang til alle e-kurs
  • Tilgang til nye e-kurs som publiseres

Kunnskapsbank

kr 300,– / mnd
Trekkes årlig
Legg til
  • Tilgang til alle artikler
  • Tilgang til nye artikler som publiseres
  • Vederlagsfri konsultasjon inntil 5 timer pr år
Les abonnementsvilkår

Har du et tema du ønsker at vi skal skrive om?

Thank you! Your submission has been received!
Det skjedde noe galt. Kontakt oss på hei@byggogprosjektjus.no hvis problemet vedvarer

Har du et tema du ønsker at vi skal skrive om?

Thank you! Your submission has been received!
Det skjedde noe galt. Kontakt oss på hei@byggogprosjektjus.no hvis problemet vedvarer